Weekly Report: June 26-July 7, 2010
City of D’Iberville
Public Works Dept; Operating Report for the week of: 6/26- 7/2
*Water & Sewer Section: Work Orders received 188 Work Orders Completed 180
(the work orders completed are not necessarily the same work orders that were received)
Significant Planned Projects:
- 51 + 7 routine system checks (water wells & lift stations)
- water meter reading (starting books #1)
- 8 flush hydrants / 0 hydrant repair / hydrants out of service: none
- 0 sewer connections & 0 water connections
Significant Unplanned Projects:
- 18 water & sewer repairs
- 15 re-reads of water meters (customer / City Hall requests)
- 50 water meter turn offs / on
- 33 water & sewer system locate requests
- 0 water & sewer taps
- Lickskillet Rd. & Boney Ave.; Major Lift Station, repairs
*Road Section: Work Orders received 25 Work Orders Completed 28
Significant Planned Projects:
- Equipment / Vehicle maintenance & repairs (8)
- I-110 Boat Launch / Marina; daily cleaning and pier maintenance (6)
- asphalt / road repairs; minor
- cleaned trash piles; 120 cu. yds. picked up and disposed to dump.
- storm drain & culvert repairs: cleaned drains throughout the City
- Build. Maintenance; roof repairs @ Public Works, City Hall, Police Dept.
Significant Unplanned Projects:
- modifications @ City Hall (20 hrs.)
- clean ditches & culverts…. City wide / prior to & after major rain event (2 days); 7.9 inches of rain on 6/30/10. Placed and retrieved 44 Barricades on flooded streets.
Summary / Comments: This reporting period included time off for Friday, Employee Appreciation Day.